Why chat groups and spreadsheets fall short
Most solar sites start with a chat group. A technician posts a photo of a tripped inverter. Someone replies "noted". Two days later nobody is sure whether it was fixed, by whom, or when. The O&M manager rebuilds the story from scrolling, and the daily report says "under rectification" for a week.
A spreadsheet tracker is better, but someone has to keep it up to date, and the person in the field rarely has a laptop. The gap between what happened on site and what the office knows is where hours of downtime hide.
Ticketing closes that gap. It is not about software for its own sake. It is about three plain facts for every job: who owns it, what state it is in, and what proves it was done.
A ticket life cycle that holds up
Keep the states few and their meaning strict. This is a life cycle that works for most O&M teams:
| State | Meaning | Who moves it on |
|---|---|---|
| Open | A problem is recorded, nobody is on it yet | Anyone who finds it, or an alert |
| Assigned | A named technician has been given the job | Operations |
| Accepted | The technician has seen it and taken it on | The technician |
| In progress | Work has started on site | The technician |
| Paused | Waiting for spares, a permit, the grid, or daylight | The technician |
| Closed | The technician says it is done, with a photo | The technician |
| Verified | Operations has checked the plant data and agrees | Operations |
| Reopened | It was not really fixed | Operations |
Three rules make this work.
- One owner at a time. A job assigned to "the site team" is assigned to nobody. Name a person. If they cannot do it, reassign it, and record that.
- Closed is not verified. The technician closes the job. Someone else confirms it from the data: the inverter is producing again, the string current is back in line. Many "fixed" faults come back within a day, and the verify step is where you catch them.
- A photo to close. A closing photo is cheap evidence: the replaced fuse, the reset display, the cleaned row. It ends most arguments before they start.
Only assign technicians to plants they actually cover. A job sent to someone four hours away is a job that waits.
What to record on every change
Every change of state should leave a line in the record: who did it, when, from which state to which. That record is what you need when a customer asks why an inverter was down for three days, or when a contract penalty is disputed.
When two people edit the same job at once, one change should not silently overwrite the other. A system that refuses the second edit and shows what changed saves arguments about who reassigned what.
Offline is not optional
Solar plants are often far from good mobile coverage, and the inverter rooms are metal boxes. If the phone app needs a signal to save "work started", the technician will skip it and fill it in later from memory, if at all.
An offline app saves each action on the phone with the phone's own time, and sends it when signal returns. The record then shows when the work really happened, not when the phone found a tower. Sending the same action twice after a dropped connection must not create a duplicate.
Permits-to-work: what they are for
A permit-to-work is a written control for jobs where someone could be hurt: work on inverters, combiner boxes, transformers, switchgear or anything that can be live. It makes sure the right equipment is isolated before work starts, that only authorised people work under it, and that the equipment is not re-energised until everyone is clear.
Solar adds a twist. You can switch off the AC side, but modules keep producing DC voltage whenever there is light. Isolation on a PV plant has to account for that.
Requirements differ by country, company and equipment, so follow your own safety rules and the applicable regulations. In general practice, a sound permit system covers these points:
- Scope. Exactly what work, on exactly which equipment. "Inverter 6, replace DC fuse in string 4", not "inverter work".
- Issuer and receiver. An authorised person issues the permit; the person doing the work receives it. They are not the same person.
- Isolation points. Every switch, breaker or disconnector that must be opened, and confirmation that each one is.
- Locks and tags. Lockout-tagout (LOTO): a personal lock and a tag on each isolation point, so nobody can switch it back on by mistake.
- Test for dead. Proving with a suitable tester that the equipment is actually de-energised before touching it.
- Hazards and controls. What else could go wrong (heat, height, stored energy, DC from modules) and what is done about it.
- Validity. When the permit was issued and when it expires. Work does not continue on an expired permit.
- Closure. Work done, people clear, locks removed, equipment returned to service, with the time recorded.
Tie the permit to the ticket
A permit on paper in a site office and a ticket on a phone are two records of the same job that can disagree. Link them. The ticket says what is wrong and who is fixing it. The permit says it is safe to fix it now. A job that needs isolation should not move to "in progress" without an active permit, and the permit should close before the ticket does.
This also gives you clean downtime records. The time between isolation and return to service is planned downtime. It belongs in the daily report as equipment unavailability, with its reason.
Planned work belongs in the same system
Not every job starts with a fault. Module cleaning, thermal scans, torque checks, vegetation cutting and inverter servicing are planned work, and they need the same tracking: who did it, when, and on which blocks. Put them in the same ticket system as breakdowns.
There is a practical reason. Cleaning changes the plant's performance ratio the following days. If the cleaning is not recorded with its date and blocks, nobody can tell whether a PR jump was the cleaning or a sensor problem, and the soiling analysis loses its anchor. The same goes for any planned outage: if it is not logged, it looks like a breakdown in the daily report.
Measures worth watching
- Time from alert to assignment.
- Time from assignment to work starting.
- Time from start to verified.
- Jobs reopened after being closed.
- Energy lost while each job was open.
The last one matters most. A slow fix on a large central inverter in May costs far more than a slow fix on a string fuse in December. Sort the queue by energy at stake, not by the order jobs came in.
Where HKDataCrest Solar fits
In HKDataCrest Solar, operations assign tickets to technicians who cover that plant. Technicians accept, start, pause and close jobs on a phone app that works offline, closing with a photo, and operations verify or reopen them. Every change is recorded with who, when and the phone's own time. A permit is tied to its ticket and records the scope, who requested and issued it, when it was issued, how long it is valid, when isolation was confirmed, and its status from requested to active to closed. See field tickets and permits and alerts.