The formula
IEC 61724-1, the international standard for photovoltaic system performance monitoring, defines PR from two yields. Both are expressed in hours, which is what makes the ratio clean.
Final yield Yf = E ÷ P0
Reference yield Yr = H ÷ G_STC
PR = Yf ÷ Yr
Where:
- E is the energy delivered over the period, in kWh. For O&M and contract purposes this is usually the export meter reading.
- P0 is the plant's rated DC capacity at standard test conditions, in kWp.
- H is the irradiation received on the module plane over the period, in kWh/m². This comes from a plane-of-array pyranometer.
- G_STC is the irradiance at standard test conditions, 1 kW/m².
Put together, the formula many teams use day to day is:
PR = E ÷ (H × P0)
with E in kWh, H in kWh/m² and P0 in kWp. The 1 kW/m² cancels the units.
A worked example
Take a made-up plant to show the arithmetic.
| Item | Value | Note |
|---|---|---|
| DC capacity, P0 | 10,000 kWp | 10 MWp plant |
| Irradiation on the module plane, H | 6.0 kWh/m² | A clear day |
| Exported energy, E | 48,000 kWh | From the export meter |
| Reference yield, Yr | 6.0 h | 6.0 ÷ 1 |
| Final yield, Yf | 4.8 h | 48,000 ÷ 10,000 |
| PR | 0.80 (80%) | 4.8 ÷ 6.0 |
Read it this way: the sunlight that day was worth six hours at full rated output. The plant delivered the equivalent of 4.8 hours. The other 20% went to temperature, inverter and cable losses, soiling, mismatch, downtime and anything else between the module and the meter.
Why PR and not just energy
Energy depends on the weather. A plant that made less this week than last week may simply have had more cloud. PR takes the sunlight out of the comparison, so a fall in PR points to something the team can look into.
PR also lets you compare plants of different sizes and in different places, within limits. Two plants in similar climates with similar equipment should have similar PRs. If one is several points lower, there is a reason.
What PR does not do is remove the effect of temperature. Modules lose efficiency as they heat up. So the same healthy plant usually shows a lower PR in a hot month than in a cool one. That is why the seasonal pattern of PR matters as much as its level.
Temperature-corrected PR
To compare PR across seasons fairly, many contracts and analysts use a temperature-corrected version. The idea is to scale the reference side by how much power the modules should have lost to heat in each interval.
PR_corr = E ÷ Σ( P0 × H_i × (1 + γ × (T_cell,i − 25 °C)) )
Here γ is the module's power temperature coefficient, a negative number per °C from the datasheet; for common crystalline silicon modules it is typically a few tenths of a percent per °C. T_cell is the cell temperature in each interval, measured with a back-of-module sensor or estimated from ambient temperature, irradiance and wind with a thermal model. The sum runs over the intervals in the period.
IEC 61724-1 describes temperature-corrected PR, and NREL's technical report on weather-corrected performance ratio (Dierauf et al., 2013) explains one widely used method in detail. Note that the NREL method does not correct to 25 °C: it corrects to the plant's own annual average cell temperature, so over a full year the weather-corrected PR comes out close to the plain PR. Correcting to 25 °C instead shifts the whole series, upward on sites where cells usually run hotter than 25 °C. If your contract has a PR guarantee, check which definition it uses before arguing about a number.
Contract PR: what the contractor controls
An O&M contractor cannot stop the grid failing or the grid operator capping export. Most O&M contracts therefore measure the contractor on a PR that leaves those events out. There are two common ways to do it:
- Add the lost energy back. Estimate the energy lost to grid outages and curtailment, and add it to E before dividing.
- Drop the affected intervals. Remove those intervals from both the energy side and the sunlight side, so they count for nothing either way.
Both are defensible. What matters is that the method is written into the contract and applied the same way every month. A guaranteed PR often carries liquidated damages when the plant falls short, so the definition has real money attached.
Mistakes that skew PR
Using the wrong capacity
PR uses DC capacity at STC. If someone divides by AC capacity, PR comes out too high on plants with a high DC-to-AC ratio. Keep the capacity on record per block, and update it when modules are replaced or added.
Counting missing data as zero
If the meter data is missing for two hours but the sunlight data is complete, a naive calculation counts two hours of sun with no energy. PR drops, and the plant looks faulty. The fix is to count sunlight only for the intervals where energy data arrived, and to mark the day as partial.
Trusting a dirty or drifting sensor
A pyranometer that is dusty or losing sensitivity reads low. Low H means high PR. A plant can look healthy for months while its sensor hides a real loss. Clean sensors on a schedule, and watch for a slow drift: on clear, event-free days, the ratio of measured sunlight to energy should wander around a level, not slide steadily one way.
Mixing horizontal and plane-of-array irradiance
A horizontal sensor (GHI) reads less than the module plane on a tilted array for much of the year. Using GHI directly as H inflates PR. If only GHI is available, convert it to the module plane with a transposition model and say so in the report.
Using inverter energy instead of meter energy
Inverter energy is measured before transformer and cable losses and auxiliary loads. PR on inverter energy will always be higher than PR on meter energy. Pick one, label it, and stick to it.
PR over a week, a month or a year
A common slip: averaging daily PRs to get a monthly PR. That gives a cloudy day the same weight as a bright one, even though the bright day produced far more energy. The right way is to sum first, then divide:
PR_month = Σ E ÷ Σ (H × P0)
with both sums over the same days and the same intervals. If the plant's capacity changed during the month, use the capacity that applied on each day. If some days are partial, apply the same rule as for a day: count sunlight only where energy data arrived. The monthly figure in the MIS report and the one in the contract calculation should come from exactly this sum, so the two always agree.
What a "good" PR is
There is no single right number. PR depends on climate, module and inverter technology, design choices and how the plant is maintained. The useful comparisons are against the plant's own design PR from its energy yield assessment, against its own history for the same month, and against similar plants nearby. A sudden drop matters more than the absolute level. A slow slide between cleanings is usually soiling.
Where HKDataCrest Solar fits
HKDataCrest Solar's performance analytics calculates PR from meter energy, plane-of-array irradiance and DC capacity, counting sunlight only for the intervals whose energy data arrived. It also shows PR without grid limits and the contract PR that leaves out grid outages and curtailment, and it flags an irradiance sensor that appears to be drifting before any report uses it. The shortfall breakdown explains what the PR gap is made of.