Expected is not the same as budget
Two baselines get mixed up all the time, and they answer different questions.
| Baseline | Built from | Answers |
|---|---|---|
| Budget (often P50) | Long-term average weather from the energy yield assessment | Is the plant earning what the business plan assumed? |
| Expected | The sunlight actually measured today, the plant's capacity and its design PR | Given today's sun, did the plant do what it should? |
The difference between budget and expected is the weather. Nobody can fix the weather, so it should never land on the O&M team's desk. The difference between expected and actual is the plant. That is the O&M team's job, and it is what this article is about.
Working out expected generation
For each interval, usually 5 or 15 minutes:
Expected kWh = H_poa × P0 × PR_design
- H_poa is the irradiation on the module plane in that interval, in kWh/m².
- P0 is the DC capacity in kWp.
- PR_design is the performance ratio the plant was designed to achieve, from its yield assessment or contract.
Sum the intervals for the day. Two rules keep this honest. First, count only intervals where energy data actually arrived; a gap in the meter feed must not count as sunlight with no energy. Second, check that the irradiance sensor is trustworthy, because every expected figure rests on it. A dusty sensor lowers expected generation and hides real losses. See performance ratio explained for the traps in more detail.
More detailed models exist. A full simulation can account for temperature, spectrum, shading and inverter efficiency curves, and tools such as the open-source pvlib library make that easier. For daily O&M, the simple model works well as long as the design PR is realistic and the same model is used every day. Consistency matters more than precision here: you are looking for changes.
The six buckets
Once you have expected and actual for each interval, the gap has to go somewhere. We use six buckets, filled in this order.
1. Grid outage
The grid was not there to take the energy. Evidence: a logged feeder trip and the export meter showing no power at the same time. A trip logged while the meter still shows export is not a grid outage for that interval. If a diesel generator kept the plant's auxiliaries alive and the plant could run only up to some limit, the energy it could not deliver is still a grid loss.
2. Grid limit (curtailment)
The grid operator ordered the plant to cap or stop export. Evidence: the written instruction, with who issued it, start and end times and the limit. During the order, the gap between expected and actual is the curtailment loss. Label it as an estimate, because nobody can measure energy that was never produced.
3. Inverter down
An inverter was not ready to produce while the grid was up. Its share of the plant's expected energy for those intervals, in proportion to its capacity, is the loss. Fault codes and the ticket that fixed it go with it as evidence.
4. Weak strings
The inverter was running but producing less than its healthy neighbours. Measure it by peer comparison: at each moment, take the output per kWp of the healthy inverters on the same plant, multiply by this inverter's kWp, and subtract what it actually made. The result is energy lost to blown fuses, failed connectors, damaged modules or new shading.
5. Soiling (dirty panels)
Dust and dirt on modules. This cannot be seen in a single interval; it shows up as a slow slide in PR between cleanings. The loss on a day is the gap between the clean-panel level and the trend line that day, times the day's sunlight and capacity. More on the method in soiling loss and when to clean.
6. Unexplained
Whatever is left. This bucket must exist and must be visible. It is the honest answer to "what else?", and a growing unexplained line is itself a finding: a sensor problem, a model problem, or a fault nobody has diagnosed yet.
Why the order matters
If two causes overlap in time, the same lost kilowatt-hour can be claimed twice. An inverter that was faulty during a grid outage did not lose anything extra: with no grid, it could not have exported anyway. Putting each interval's gap into one bucket only, in a fixed priority, prevents double counting.
The order runs from outside causes to inside causes. Outside causes (grid outage, grid limit) are out of the O&M team's control. Inside causes (inverter down, weak strings, soiling) are theirs to fix. Taking outside causes first means the contractor is never charged for energy the grid would not have accepted.
A worked example
A made-up day on a plant, to show how the buckets add up.
| Line | kWh | Notes |
|---|---|---|
| Expected | 50,000 | From measured irradiance, capacity and design PR |
| Actual export | 44,000 | From the export meter |
| Shortfall | 6,000 | To be explained |
| Grid outage | 1,500 | Feeder trip 12:10–12:55, meter at zero |
| Grid limit | 2,000 | Export cap order 13:30–15:00 (estimate) |
| Inverter down | 1,200 | One inverter tripped 09:40, reset 11:15 |
| Weak strings | 400 | Another inverter below its peers all day |
| Soiling | 600 | From the PR trend since the last cleaning |
| Unexplained | 300 | What is left |
The six lines sum to the 6,000 kWh shortfall. 3,500 kWh was outside the plant's control. 2,200 kWh was the O&M team's to recover, and each line points to a specific action: a recurring inverter trip to investigate, a string fault to find on site, a cleaning to schedule. Multiply each line by the tariff and you have the cost of each cause.
Gaps in the data
Real data has holes. A comms outage at the plant, a missing file from one block, an inverter that stopped reporting while it kept running. The rule is simple: a missing value stays missing, never zero. Mark the day as partial, say how much is missing, and do not put the unknown energy into any bucket. Guessing turns a data problem into a fake fault, or hides a real one.
Making it stick in the daily report
The breakdown is only useful if people see it every morning. Put it in the daily generation report, not in a separate analysis that someone opens once a month. Show the lines in kWh and in money. Link each line to its evidence: the trip log, the curtailment order, the ticket. When an owner asks "why was yesterday low?", the answer should already be on the page they are reading. Our guide to the daily generation report format shows where it goes.
Where HKDataCrest Solar fits
HKDataCrest Solar works out expected generation for every interval from measured plane-of-array irradiance, DC capacity and design PR, and puts each interval's gap into exactly one bucket in the order above: grid outage, grid limit, inverter down, weak strings, dirty panels, unexplained. The buckets add up, they are valued at the tariff, and missing data is never filled in. The breakdown appears in the daily and monthly reports.