Start with the question, not the tag list
A modern plant can expose thousands of data points. Most teams do not need most of them day to day. Monitoring is useful when it answers three questions quickly:
- Is every plant producing what today's sunlight allows?
- If not, where is the energy going, and is it something we can fix?
- Can we trust the numbers we are looking at?
Everything below serves one of those three. If a data point does not, it can live in SCADA for engineers to dig into when needed.
1. Exported energy at the meter
This is the number the plant is paid on. Track it from the export meter, not only from the inverters. Inverter totals are always a little higher than meter export, because of transformer and cable losses and auxiliary consumption. If you report inverter energy as generation, your figures will never match the utility's.
Track it at the finest interval the data allows, typically 5 or 15 minutes. Daily totals hide the shape of the day, and the shape is where most faults show up: a flat top on a clear day points to clipping or a grid limit; a step down at noon points to a trip.
2. Irradiance on the module plane
Without irradiance you cannot tell a cloudy day from a faulty plant. Track plane-of-array (POA) irradiance, often called GTI, from a pyranometer mounted at the module tilt. If the plant has only a horizontal sensor (GHI), it can be converted to the module plane with a transposition model, but that adds uncertainty.
Watch the sensor as closely as the plant. A dusty or drifting pyranometer reads low. That makes the plant's performance ratio look better than it is, and a real loss stays hidden. Two simple checks catch most problems: compare the sensor with clear-sky irradiance on the clearest days, and look for a slow, steady drift in the ratio of sunlight to energy. IEC 61724-1 sets out sensor classes and maintenance for monitoring systems; it is worth reading before you buy or replace sensors.
3. Inverter status and output
For each inverter, track whether it is running, its AC power, its energy and its fault codes. The question to answer is simple: was it ready to produce whenever there was sun and grid? An inverter that tripped at 11:00 and was reset at 15:00 lost the best hours of the day. That needs to be visible as lost energy, not just as a fault code in a log.
Keep the fault-code history. A single trip is noise. The same code three times in a week on the same unit is a pattern, and patterns are where maintenance planning starts.
4. Strings and blocks against their peers
An inverter can be running and still underperforming because some of its strings are weak or dead: a blown fuse, a damaged connector, shading from a new obstruction. These faults are easy to miss because nothing trips.
The practical test is peer comparison. At the same moment, inverters or strings on the same plant see roughly the same sunlight. Normalise each one's output by its capacity (kW per kWp) and compare it with its healthy neighbours. A unit that sits consistently below the group has a problem worth a site visit. This works even without string-level current data, at inverter level, though string data makes the fault easier to find.
5. Availability: plant and grid, separately
Availability is the share of time the plant could produce when it should have. Track two numbers, not one:
- Grid availability: the share of daylight time the grid was there to take the energy.
- Plant availability: the share of daylight, grid-up time that the inverters were ready, weighted by capacity.
Keeping them apart matters because O&M contracts usually hold the contractor responsible for plant availability, not for grid outages. One blended number turns every grid failure into an argument.
6. Grid limits and curtailment
When the grid operator orders a plant to cap or stop export, the plant loses energy through no fault of its own. Record every instruction: who issued it, when it started and ended, and the limit. In India that is usually the SLDC or the DISCOM; elsewhere it is the network or system operator. The record is the evidence for any later claim, and it keeps curtailment out of the contractor's performance figures.
7. The health of the data itself
This is the item most monitoring setups forget. For every plant, track:
- Freshness: when the last reading arrived.
- Completeness: what share of the day's daylight intervals actually arrived.
- Rejected values: duplicates and readings outside a sensible range that were dropped.
- Meter against SCADA: whether the billing meter and the SCADA or portal figures agree.
A missing reading must stay missing. If a monitoring tool fills a gap with zero, the day's PR drops and the plant looks broken. If it fills it with an estimate without saying so, a real outage can vanish. Mark the day as partial and say how much is missing.
Turning measurements into alerts
Tracking is half the work. The other half is deciding what wakes someone up. Two alerts earn their place on every plant: a trip, where the plant or an inverter stops while there is sun and grid, and data loss, where readings stop arriving. Both are clear, both need action, and both get worse the longer nobody notices.
Be careful with alerts built on percentages. "Output below 80% of expected" fires on every passing cloud if it is checked interval by interval. Check over a longer window, only during daylight, and only when the irradiance data itself is healthy. Make every alert close itself when the condition clears, and send one reminder if it stays open, not one email every five minutes. A team that receives fifty alerts a day stops reading them, and then misses the one that mattered. More on this in inverter trip and SCADA-down alerting.
How to lay out the screen
Put problems first. The most useful portfolio view sorts plants by status: no data, then warnings, then late data, then normal. Within each status, sort by how far below expected the plant is. A control room should be able to scan it in seconds.
For each plant, a short row is enough: today's energy, percent of expected so far (with a "partial" flag if data is incomplete), yesterday against budget, PR, availability, open tickets, any active grid limit, and when data last arrived. Clicking through should show the day's power curve against expected, the inverter table and the event log.
What not to track daily
Some numbers are better reviewed weekly or monthly. Module degradation moves slowly and needs long, clean data to measure. Transformer and switchgear condition depends on test results that arrive periodically. Long-term yield against the P50 budget is a monthly conversation. Put them in the monthly report, not on the control-room screen, where they add noise.
Where HKDataCrest Solar fits
HKDataCrest Solar's monitoring puts every plant on one screen, problems first, whatever the SCADA brand. It tracks energy against expected, PR, plant and grid availability, grid limits logged from the phone, and data completeness, and it flags a drifting irradiance sensor before reports use it. Missing data stays missing. When a plant trips or its data stops, alerts reach the team.