What a DGR is for
The DGR is the first thing an owner reads about a plant each morning. It answers three questions. How much did the plant make? Was that what the sunlight allowed? If not, why not?
It is also a record. Months later, when an invoice is disputed or a guarantee is tested, the DGRs are the evidence. A figure typed in wrong on a Tuesday can turn into an argument about money in the monthly settlement. That is why the format matters less than two habits: every number should come from a reading you can point to, and every lost hour should carry a reason.
A common DGR format, field by field
This is a typical layout for a utility-scale or large commercial plant. It is a common format, not a standard. Your contract or owner may ask for more, fewer or differently named fields.
| Field | Unit | Where it comes from | Why it is there |
|---|---|---|---|
| Plant name, date, DC and AC capacity | kWp, kW | Plant master data | So the report stands on its own |
| Export energy | kWh | Main export meter (ABT or billing meter) | The number the plant is paid on |
| Import energy | kWh | Same meter, import register | Night-time and auxiliary consumption |
| Net export | kWh | Export minus import | What actually counts in most settlements |
| Meter opening and closing readings, MF | register units | Meter, read at a fixed time | Lets anyone recompute the energy |
| Inverter generation | kWh | Inverters or SCADA | Cross-check against the meter; spots losses between inverter and meter |
| Irradiation on the module plane (GTI) | kWh/m² | Plant pyranometer | The sunlight the plant had to work with |
| Performance ratio (PR) | % | Calculated | Output relative to the sunlight |
| Plant availability | % | Calculated from inverter status | How much of the plant was ready to generate |
| Grid availability | % | Calculated from grid status | How much of the day the grid could take power |
| Breakdowns and outages, with start and end times | hh:mm | SCADA events and site log | The cause behind any shortfall |
| Curtailment instructions | MW, hh:mm | SLDC, DISCOM or customer instruction | Energy lost for reasons outside the plant |
| Cleaning and maintenance done | rows or blocks | Site log | Explains PR changes on the following days |
| Remarks | text | Site engineer | Anything the numbers do not say |
How the main numbers are worked out
Energy from meter readings
Most billing meters show a register, not kWh directly. The energy for the day is the difference between two readings, times the multiplying factor (MF) of the meter's current and voltage transformers.
Energy (kWh) = (closing reading − opening reading) × MF
Read the meter at the same time every day. Write both readings in the report, not just the result. When a register rolls over past its last digit, the subtraction must allow for it. A report that shows only "export: 41,230 kWh" cannot be checked. One that shows the two readings and the MF can.
Performance ratio
Performance ratio compares the energy the plant produced with what its rated capacity would give in the sunlight it received. The basic form, as used in IEC 61724, is:
PR = energy exported ÷ (GTI in kWh/m² × DC capacity in kWp)
GTI here is irradiation on the module plane over the day, and the formula assumes a reference irradiance of 1 kW/m². So a plant of 10,000 kWp that received 5.5 kWh/m² and exported 44,000 kWh has a PR of 44,000 ÷ (5.5 × 10,000) = 80%. For more on PR, including the temperature-corrected version, see performance ratio explained.
Two things to be strict about. First, if part of the day's data is missing, count the sunlight only for the intervals you have energy for. Otherwise a data gap shows up as a PR drop that never happened. Second, say whether the PR shown includes or excludes curtailment. Many contracts measure the contractor on a PR that leaves out grid outages and grid limits, because the contractor cannot control them.
Availability
Plant availability is the share of daylight time, when the grid was up, that the plant's inverters were ready to run. It is usually weighted by capacity, so one small inverter down counts less than a large one. Grid availability is the share of daylight time the grid could take power. Keeping the two apart matters. A grid outage should never count against the plant.
The part most DGRs get wrong: the reasons
Most DGRs state the shortfall. Few explain it. "PR 74%, below target" tells the owner nothing they can act on. A useful DGR splits the gap between expected and actual into causes:
- Grid outage: the grid was down and the plant could not export.
- Curtailment: the grid operator or customer limited output.
- Inverter or equipment breakdown: part of the plant was not ready.
- Weak strings: an inverter ran, but below its healthy neighbours.
- Soiling: dust on the modules, shown as a slow slide in PR between cleanings.
- Unexplained: what is left. Show it, do not hide it.
The causes should add up to the gap. If they do not, the report is hiding a number somewhere. The method is covered in generation vs expected: how to explain every shortfall.
Every outage and breakdown line should carry a start time, an end time and the equipment affected. "Inverter 3 tripped, restored" is not enough. "INV-03 tripped 11:42, restored 13:15, DC insulation fault, reset by site" is.
Common mistakes
- Zeros for missing data. If SCADA stopped at 14:00, the afternoon is unknown, not zero. Mark the day partial and say how much is missing.
- A dirty or drifting sensor. A pyranometer that reads low makes PR look high and hides real losses. If PR suddenly beats the design value for weeks, check the sensor before celebrating.
- Inverter energy used instead of meter energy. Inverter totals are useful for comparison, but the meter is what is billed. Report both, and say which one PR uses.
- Curtailment left out. If the SLDC or DISCOM limited the plant and nobody logged the instruction, the loss looks like the contractor's fault.
- Manual copying. Every figure typed from one screen into a spreadsheet is a chance to get it wrong. The fewer hand steps, the fewer disputes.
- Sent late. A DGR that arrives in the afternoon is history, not a report. Aim to send it early in the morning for the previous day.
How to get it out on time
The work of a DGR is mostly gathering: pulling SCADA files, reading meters, collecting the site log, checking curtailment messages. The arithmetic is quick once everything is in one place.
A workable routine for a team running several plants:
- Get the previous day's plant data in automatically overnight, from SCADA files, a push feed or a live connection.
- Have the site record the meter readings and any outages, curtailment or cleaning as they happen, not at the end of the day.
- Let the system draft the report and flag anything odd: a missing block file, meter and inverter energy far apart, a suspect sensor.
- An engineer reviews the flags, corrects what needs correcting, and sends.
- Keep every correction with who made it and when, so a later reader can see what changed.
The monthly report should then be built from the same daily figures, not compiled separately. See what an owner needs every month.
Keep the client's format
Owners and lenders often have their own DGR template, built up over years, with their logo, their field names and their formulas. Asking them to switch to yours rarely goes well. It is better to fill their template with your numbers, leaving their formulas and layout as they are. That way the report looks familiar to the reader while the figures behind it come straight from the data.
Where HKDataCrest Solar fits
HKDataCrest Solar drafts each plant's DGR from its own data, with generation against expected, PR with and without grid limits, availability, and every shortfall split into causes. Missing data is shown as missing, never zero. An engineer checks and sends it, and it can be written into the contractor's own Excel template with that template's formulas untouched. See solar reports and MIS and performance analytics.