Who reads it, and what they decide
The daily report is for the operations team. The monthly MIS report is for people who do not look at plants every day: the owner's asset manager, the finance team, sometimes a lender or an investor. They have three questions:
- Did we make the money we expected?
- If not, whose problem was it: the weather, the grid, or the plant?
- What is being done about it, and will it happen again next month?
Everything in the report should serve one of those questions. A twenty-page MIS full of charts that answer none of them is worse than a two-page one that answers all three.
Budget and expected are different things
This is the most useful distinction in a monthly report, and the one most often blurred.
- Budget is what the plant was forecast to make this month, usually from the energy yield assessment done before it was built (often a P50 figure). It assumes typical weather.
- Expected is what the plant should have made given the sunlight it actually received this month. It is worked out from the measured irradiation, the plant's capacity and its design performance ratio.
The gap between budget and expected is the weather. Nobody can fix that. The gap between expected and actual is the plant and the grid, and that is where the operations questions are. A report that only shows "actual vs budget" mixes the two and invites the wrong conversation. A cloudy month looks like poor O&M, and a sunny month hides real losses.
Label every percentage with what it is measured against. "92%" means nothing. "92% of budget, 98% of expected" tells the story in one line: a dull month, a healthy plant.
What goes in, section by section
1. Portfolio summary
One table, one row per plant. Columns that earn their place: generation (MWh), % of budget, % of expected, PR, plant availability, energy lost to causes inside the plant, and the JMR difference. Sort so the plants needing attention are at the top.
2. Generation and sunlight
Monthly generation, irradiation on the module plane (kWh/m²), and a daily chart of both. The chart quickly shows whether a low month was a few bad days or a slow decline. Show days with missing data as gaps, not zeros, and state the month's data completeness.
3. Performance ratio and availability
PR for the month, with the formula stated. If the O&M contract has a PR guarantee, show the contract PR as well. Contract PR usually excludes grid outages and grid limits, because the contractor cannot control them. Plant availability and grid availability go side by side, never combined.
If the contract carries liquidated damages for a PR or availability shortfall, show the calculation, not just the result. Owners and contractors both want to check it.
4. Losses by cause
This is the heart of the report. Start from expected generation and step down to actual, one cause at a time:
| Step | What it means | Who it belongs to |
|---|---|---|
| Grid outage | The grid was down and the plant could not export | Outside the plant |
| Curtailment | Output was limited by the grid operator or customer | Outside the plant |
| Equipment downtime | Inverters, transformers or other equipment not ready | Plant / O&M |
| Weak strings | Running, but below healthy neighbouring equipment | Plant / O&M |
| Soiling | Dust on the modules between cleanings | Plant / O&M |
| Data gap | Hours with no data: unknown, not guessed | Shown separately |
| Unexplained | What is left after the above | To be investigated |
Show each step in energy and in money at the tariff. Link each step to the events behind it: which outages, which curtailment orders, which inverter faults. If a reader cannot trace a number to an event, they will not trust it. The daily method is in how to explain every shortfall.
5. Meter reconciliation (JMR)
In India, the plant's energy for billing is usually settled on a joint meter reading (JMR) taken by the DISCOM and the plant at the month's end. The MIS should put the JMR figure next to the plant's own meter or SCADA total and show the difference in kWh, in percent and in money. A difference of more than a small fraction usually means a meter problem, a reading error or a CT/PT ratio mismatch. It should be chased before the invoice goes out, not after.
Elsewhere the name differs, but the principle holds. Reconcile your own figure with the figure you are paid on, every month.
6. Field work and open issues
How many tickets were raised and closed, which are still open, and how long the important ones took. Cleaning cycles done against the cycles the contract asks for. Any equipment waiting for spares. Keep it short. The owner wants to know what will still be a problem next month.
7. Data quality
A short line on data completeness, sensor checks and any corrections made to daily figures during the month, with who made them. This is the section most reports leave out, and the one that makes the rest believable. If the irradiance sensor was drifting, the PR for the month may be wrong, and the reader should know.
Plants with several offtakers
Group captive and open-access plants often have several consumers, each owning or buying a share. Each consumer should get their own monthly report showing energy and money at their share. Ratios such as PR and availability belong to the plant as a whole and should not be scaled. More in reporting for several offtakers.
Mistakes that cost trust
- One percentage with no base. Always say "of budget" or "of expected".
- A big "other" losses line. If a third of the lost energy is unexplained, say so plainly and say what is being done to find it. Do not spread it across the other causes.
- Curtailment missing. If grid limits were not logged during the month, they turn up as plant losses. The contractor pays for the grid's decisions.
- Charts without a point. Every chart should answer a question in the report's opening summary. If it does not, cut it.
- No comparison with last month. A single month on its own hides trends. Show the previous months beside it, so a slow decline is visible before it becomes a large one.
Build it from the daily figures
The commonest MIS problem is a monthly total that does not match the sum of the month's DGRs. It happens when the monthly report is compiled separately, from a different export, by a different person. Build the MIS from the same stored daily figures the DGRs used, including any corrections, and the two will always agree.
And send it on a fixed day. A monthly report that turns up three weeks into the next month has already lost most of its value.
Where HKDataCrest Solar fits
HKDataCrest Solar builds monthly reports from the same daily figures as the DGRs: generation against budget and expected, PR and contract PR, availability, losses by cause, JMR reconciliation and open field work. Reports are emailed automatically, and plants shared by several customers produce one report per customer at their share. See reports and MIS and shared plants.